NEBRASKA

 

About the Author  |  This Book's Table of Contents  |  Order this Book  |  Seminars  |  Sponsors  |  Return to Map

NEBRASKA CONSTRUCTION LAW
TABLE OF CONTENTS

 

 

Preface and Acknowledgements........................................................ xv     

About the Author................................................................................ xvii                             

 

CHAPTER ONE

LICENSING

 

1.1 INTRODUCTION............................................................................ 1                 

1.2       OBTAINING A CERTIFICATE OF AUTHORITY – OUT-OF-STATE FIRMS                     2         

1.3 CONTRACTOR LICENSING REQUIREMENTS.......................... 2

1.3.1    Resident Contractors – Contractor Registration Act..... 2

            1.3.1.1 Scope and Applicability................................................. 2

      1.3.1.2 Registration Requirements................................ 3

1.3.1.3 Penalties for Noncompliance............................ 4

1.3.2    Nonresident Contractors – Registration by Nonresident Contractors Act     5         

            1.3.2.1 Scope and Applicability................................................. 5

1.3.2.2 Registration Requirements................................ 6

1.3.2.3 Penalties for Noncompliance............................ 7

1.4 ENGINEERS AND ARCHITECTS................................................. 8

1.4.1    Engineers and Architects Regulation Act................ 8

1.4.2    Design-Build Under the E&A Act............................. 9

1.5       ELECTRICAL CONTRACTORS – NEBRASKA STATE ELECTRICAL ACT         10                   

      1.5.1    Scope and Applicability..................................................... 10

1.5.2    State Electrical Division......................................... 10

1.6       LOCAL REQUIREMENTS OF SPECIFIC CONTRACTORS 11

1.7       CONCLUSION........................................................................ 12     

 

CHAPTER TWO

BIDDING

 

2.1 INTRODUCTION.......................................................................... 15                 

2.2       COMPETITIVE BIDDING....................................................... 15     

2.2.1    Private Projects........................................................... 15     

2.2.2    Public Projects............................................................. 18     

2.2.2.1 Statutory Provisions Regarding Competitive Bidding            19       

2.2.2.2 No Bid Requirements...................................... 19

2.2.2.3 Lowest and/or Best Bid Awards ...................... 20

2.2.2.4 Lowest Responsible Bid Awards..................... 20

2.2.2.4.1  Responsive............................................ 21

2.2.2.4.2  Responsible........................................... 23

2.2.2.4.3  Price....................................................... 25

2.2.2.5 Prequalification................................................ 27

2.2.2.6 Unbalanced Bids.............................................. 28

2.3 BID ERRORS................................................................................ 30                             

      2.3.1    Contractor’s Bid................................................................. 30

2.3.2    Subcontractor Quotations.................................................. 31

2.4       BIDDING PROCEDURES...................................................... 33     

2.5       BID PROTESTS   ................................................................... 34     

2.5.1    Who Can Protest......................................................... 34     

2.5.2    Obtaining Public Documents....................................... 35

2.5.3    Where to Protest.......................................................... 35     

2.5.4    When to Protest........................................................... 35     

2.5.5    What to Protest............................................................ 36     

2.5.5.1 Late Bids................................................................ 36     
2.5.5.2 Bid Responsiveness.............................................. 36
2.5.5.3 Faulty Solicitation – Restriction on Competition and Alternates         36       

2.5.6    What Relief Is Available............................................... 37

2.5.7    Impact on the Project from the Successful Bidder’s Standpoint                   38       

2.5.7.1 Distinction Between Irregular and Ultra Vires Contracts        38       

2.5.7.2 Contracts Executed as an Ultra Vires Act Will Preclude any Payments Under the Contract      39

2.5.7.3 An Irregular Contract Will Allow the Successful Bidder to Recover Its Reasonable Costs But May Preclude the Recovery of Overhead and Profit            39                   

2.5.7.4 The Successful Bidder Must Understand and Be Prepared to Accept the Risks Associated with the Project................................................ 42

2.6 CONCLUSION.............................................................................. 42                             

 

CHAPTER THREE

THE ARCHITECT/ENGINEER

 

3.1 INTRODUCTION.......................................................................... 45                 

3.2 REGULATION OF ARCHITECTURE AND ENGINEERING..... 45

      3.2.1    Generally........................................................................... 45

      3.2.2    Professional Landscape Architects................................... 46

3.2.3    Regulation of Design Professionals in Design-Build Projects.           46

3.3 PROCUREMENT OF DESIGN PROFESSIONAL SERVICES. 47

      3.3.1    Private Projects................................................................. 47

3.3.2    Public Projects....................................................... 47

      3.3.2.1  State Agencies................................................ 47

3.3.2.2 Counties.......................................................... 48

3.3.2.3   Local Bodies........................................................ 48

3.3.2.4  Specialty Projects................................................. 49

3.4       AGREEMENTS BETWEEN THE OWNER AND THE DESIGN PROFESSIONAL                       49

3.5 ARCHITECT-CONSULTANT AGREEMENTS........................... 50

3.6 THE ARCHITECT/ENGINEER’S LIABILITY............................... 50

      3.6.1    Historical Background....................................................... 51

3.6.2    Assignment of Claims............................................ 52

      3.6.3    Liability to the Owner Arising from Design Services......... 52

3.6.3.1 Contract Claims by the Owner........................ 53

3.6.3.1.1  Improper/Defective Design............. 53

3.6.3.1.2  Implied or Express Warranty........... 53

3.6.3.1.3  Time to Perform Design Services... 54

3.6.3.1.4  Cost Estimates................................. 55

3.6.3.2 Tort Claims by the Owner............................... 55

3.6.4    Claims By Other Project Participants.......................... 56

3.6.4.1 Contract Claims............................................... 56

3.6.4.2 Third-party Beneficiary Claims........................ 56

3.6.4.3 Tort Claims...................................................... 57     

3.6.5    Statutory or Regulatory Basis for Tort Liability............ 58

3.6.5.1 Building Standards........................................... 58

3.6.5.2 Americans with Disabilities Act (“ADA”)................ 59

3.6.5.3 Occupational Safety and Health Act..................... 59

3.7       LIABILITY ARISING FROM CONTRACT ADMINISTRATION SERVICES           60                               

3.7.1    Statutory Protection From Site Safety Claims............ 60

3.6.3.3 Inadequate Inspection of Work.............................. 61

      3.7.3    Shop Drawings  ................................................................ 62     

3.7.4    Withholding Certification of Payment Application............. 63

3.7.5    Improper Certification of Payment Applications............... 63

3.6.3.6 Exculpatory Clauses.............................................. 64

3.6.4    Liability to the Contractor................................................... 64

3.7 LEGAL AND CONTRACTUAL DEFENSES TO LIABILITY........ 65

3.7.1    Statutory and Judicial Defenses to Liability....................... 65

3.7.1.1 Statute of Limitations and Statute of Repose . 65

3.7.1.2 Economic Loss Doctrine................................. 68

3.7.1.4 Impossibility / Impracticability................................ 69

      3.7.2    Contractual Defenses to Liability....................................... 69

3.7.2.1 Contractual Waiver of Subrogation....................... 69

3.7.2.2 Indemnification Clauses........................................ 70

3.7.2.3 Limitations of Liability / Damages.......................... 70

3.7.2.4 No Damages for Delay Provisions........................ 71

3.7.2.5 Requirement for a Certificate of Merit.................. 72

3.8 CONCLUSION.............................................................................. 72                 

 

CHAPTER FOUR

THE OWNER

 

4.1              Introduction.................................................................... 81

4.2              Warranty of Plans and Specifications............... 81

4.2.1        The Spearin Doctrine and Related Nebraska Cases.. 81

4.2.2        Superior Knowledge Doctrine...................................... 84

4.2.3        Implied Obligations...................................................... 84

4.2.3.1  Implied Warranty of Workmanlike

Construction..................................................... 84     

4.2.3.2  Commercial Availability................................... 87

4.2.3.3  Sufficiency Of Materials.................................. 87

4.2.3.4  Compliance with Codes and Covenants......... 87

4.3              Duty Not to Delay, Hinder, or Interfere with the Contractor’s Performance  87

4.3.3        Specific Types of Owner-Caused Delay.................... 89

4.3.3.4  Defective Specifications.................................. 89

4.3.3.5  Untimely Issuance of Notice to Proceed......... 89

4.3.3.6  Failure to Make the Project Site Available...... 91

4.3.3.7  Owner’s Delay in Acting on Shop Drawings and Submittals 93

4.3.3.8  Owner’s Delay in Supply or Removal                of Materials 94

4.3.3.9  Owner’s Issuance of Unreasonable or  Improper Stop Order           96       

4.3.3.10    Owner’s Excessive Inspection and Unreasonable Performance Demands           97

4.3.3.11       Owner’s Delay in Issuing Change Orders... 99

4.4              Owner’s Material Change in the Contract..... 100

4.5              Conclusion...................................................................... 100                 

 

CHAPTER FIVE

THE CONTRACTOR AND THE CONSTRUCTION CONTRACT

 

5.1              INTRODUCTION.................................................................. 105     

5.2              THE CONSTRUCTION CONTRACT.................................. 105

5.2.1        Contract Pricing Structure......................................... 106

      5.2.2    Integration Clause............................................................ 107     

5.2.3    Site Visit........................................................................... 108                 

      5.2.4    Order of Precedence Clause.......................................... 108

      5.2.5    Recitals............................................................................ 109                             

      5.2.6    Permits and Fees............................................................. 109     

      5.2.7    Owner’s Right to Carry Out the Work............................. 109

5.2.8    Review of Contract Documents and Field Conditions by Contractor            109                 

5.2.9    Compliance with Codes and Ordinances.................. 110

5.2.10  Contractor’s Construction Schedule.......................... 110

      5.2.11  Shop Drawings, Product Data and Samples................... 111

5.2.12  Aesthetic Determination.................................................. 112

5.2.13  Claims and Disputes – Decision of Architect or Engineer                 112     

5.2.14  Differing Site Conditions............................................ 113

5.2.15. Changes in the Work................................................. 113     

      5.2.16  Time................................................................................. 113                             

5.2.17  “Lien-Free” Provisions............................................... 113

5.2.18  “Work Through Disputes” Clause.............................. 114

5.2.19  Payments  ................................................................. 115

5.2.19.1  Progress Payments and Retainage.................. 115

5.2.19.2  Final Payment................................................... 116

      5.2.20  Statute of Limitations....................................................... 117

            5.2.20.1  Claims Against the State........................................ 118

            5.2.20.2  Claims Against Counties......................................... 119

            5.2.20.3  Municipal Claims.................................................... 119

                  5.2.20.3.1  Cities of the Metropolitan Class..................... 119

                  5.2.20.3.2  Cities of the Primary Class............................ 119

5.2.20.3.3  Cities of the First Class................ 119

5.2.20.3.4. Cities of the Second Class and Villages   120

      5.2.21  Termination     ................................................................. 120     

      5.2.22  Attorneys Fees................................................................. 123     

5.2.23  Contract Interpretation..................................................... 123

5.2.24  Ambiguity......................................................................... 123                 

5.2.25  Reasonable Construction................................................ 124

5.2.26  Give Meaning to All Terms.............................................. 124

5.2.27  Contra Proferentem: Ambiguous Terms are Construed against the Drafter 124     

5.2.28  Missing Terms and Details.............................................. 125

5.3 CONCLUSION............................................................................ 126                 

 

CHAPTER SIX

THE SUBCONTRACTOR

 

6.1 INTRODUCTION........................................................................ 131                 

6.2       DISTINCTION BETWEEN SUBCONTRACTORS AND SUPPLIERS        131                             

6.3 BIDDING..................................................................................... 132                             

6.3.1    Reliance on Subcontractor Quotes................................. 132

6.4 SUBCONTRACTING ................................................................. 134     

      6.4.1    Deductive Changes  ....................................................... 134     

6.5 Time OF PERFORMANCE....................................................... 135     

6.5.1    Actual Acceleration.............................................. 135     

6.5.2    DELAY............................................................................. 136                 

6.6 PAYMENT.........................................................................................       136                 

6.6.1    “Pay When Paid” Clauses............................................... 136

6.6.2    “Pay If Paid” Clauses....................................................... 137     

6.7 PROMPT PAYMENT REQUIREMENTS.................................. 137

6.7.1    Nebraska Prompt Payment Act  .............................. 137

6.7.2    Prompt Payment In Private Contracts  .......................... 138

6.8 CRIMINAL PENALTIES.............................................................. 138     

6.9       CONTRACTOR’S WARRANTY OF PLANS AND SPECIFICATIONS       138                 

6.10     CONTRACTOR’S DUTY TO PROVIDE INFORMATION.. 139

6.11     CONTRACTOR’S DUTY NOT TO HINDER, DELAY OR INTERFERE     139                             

6.12     ASSIGNMENT OF SUBCONTRACT.................................. 140

6.13     SUBCONTRACTOR CLAIMS AND DISPUTES................. 140

6.13.1 Pass-Through and Liquidating Agreements.............. 140

6.13.2 Pass Through of Subcontractor Claims Against the State     141

6.13.3 Flow Down Provisions............................................... 142

6.13.4 Site Safety........................................................... 142                 

6.13.5  Hold Harmless and Indemnity Clauses........................... 142

6.13.6 Subcontractor’s Liability to Contractor...................... 143

6.13.7  Subcontractor’s Liability to the Owner or Subsequent Owners         143                 

6.13.8 Termination.......................................................... 144                 

6.14     CONCLUSION...................................................................... 144                 

 

CHAPTER SEVEN

CHANGES IN THE WORK

 

7.1 INTRODUCTION........................................................................ 149                 

7.2       THE CHANGES CLAUSE.................................................... 149     

            7.2.1    Changes Clause in Standard Form Contracts.......... 149

      7.2.2    Requirement for Written Order........................................ 150

7.2.3    Notice Requirement............................................. 153     

7.2.4    Authority to Issue Change................................... 154

7.3 CONSTRUCTIVE CHANGES.................................................... 158

7.3.1    Disputes over Contract Interpretation during Performance   159                 

7.3.2    Government (Owner) Interference or Failure to Cooperate              160     

7.3.3    Defective Plans or Specifications....................... 160

7.3.4    Nondisclosure of “Superior Knowledge”.............. 161

7.3.5    Constructive Acceleration................................... 161     

7.4 DEDUCTIVE CHANGES............................................................ 162     

7.5 LIMITATIONS ON CONTRACT CHANGES............................. 162

7.5.1    Cardinal Changes and Abandonment................. 162

7.5.2    Reservation of Rights.......................................... 164     

7.6 PRICING CHANGED WORK..................................................... 164     

7.6.1    The Cost of Changed Work................................. 165     

7.6.2    The Impact of Changed Work on Unchanged Work Activities          166                 

7.6.3    Impacts of Multiple and Overlapping or Concurrent Changes and Delays   166     

7.7       CHANGE ORDER DOCUMENTATION AND ELEMENTS OF PROOF    167                             

7.8 CONCLUSION............................................................................ 168                 

 

CHAPTER EIGHT

Differing Site Conditions

 

8.1 INTRODUCTION........................................................................ 173                 

8.2 PURPOSE OF DIFFERING SITE CONDITION CLAUSES .... 173

8.3       CONTRACTOR’S RIGHT TO RELY ON OWNER’S REPRESENTATION OF CONDITIONS    176

8.3.1    Duty to Investigate Site.................................................... 176

8.3.2    Duty to Disclose............................................................... 177     

8.3.3    Disclaimer........................................................................ 177                 

8.4 NOTICE....................................................................................... 178                             

8.5 CONTRACTUAL REMEDIES.................................................... 179     

8.5.1    Type I Conditions............................................................. 179     

8.5.2    Type II Differing Conditions............................................. 181

8.6 ALTERNATIVE REMEDIES....................................................... 181     

8.7       CHANGED CONDITIONS NOT COVERED BY THE “CHANGED CONDITIONS” CLAUSE      182

8.7.1    Acts of God...................................................................... 183                 

8.7.2    Conditions Subsequent to Contract................................. 183

8.7.3    State Law......................................................................... 183                 

8.8 CONCLUSION............................................................................ 183                 

 

CHAPTER NINE

DAMAGES AND DELAYS

 

9.1 INTRODUCTION........................................................................ 189                 

9.2 THE OWNER’S DAMAGES....................................................... 189                 

9.2.1    Contractor’s Defective or Incomplete Performance....... 189

9.2.2    Contractor’s Late Completion.......................................... 190

9.2.2.1 Actual Damages – Lost profits............................ 190

9.2.2.2 Liquidated Damages............................................ 191

            9.2.3.3 Duration Related Actual Damages............................ 191

9.2.2.4 Limitations on Damages ..................................... 191

9.3 THE CONTRACTOR’S DAMAGES........................................... 194

9.3.1    Late Payment Damage................................................... 194

      9.3.2    Termination Damages..................................................... 196

9.3.3    Delay / Inefficiency Damages......................................... 196

9.3.3.1 Non-Excusable Delays........................................ 197

9.3.3.2 Excusable But Non-Compensable Delays ......... 197

9.3.3.3 Excusable and Compensable Delays................. 198

9.3.3.3.1... Delay In Issuing Notice To

Proceed....................................... 198

9.3.3.3.2... Delayed Administration Of Change Orders         199

9.3.3.3.3... Failure to Provide Site Access.... 200

9.3.3.3.4... Failure to Properly Schedule

Work ........................................... 200

9.3.3.3.5... Late Drawings.............................. 201

9.3.3.3.6... Work Suspensions....................... 201

9.3.4    Acceleration Claims......................................................... 201     

9.3.4.1 Actual or Ordered Acceleration........................... 202

9.3.4.2 Constructive Acceleration................................... 203

9.3.5    Concurrent Delays........................................................... 204     

9.3.6    Elements of Contractor’s Damages................................ 205

9.3.6.1 Direct Job Cost.................................................... 205

9.3.6.2 Home Office Overhead Costs............................ 205

9.3.6.3 Inefficiency Costs................................................ 205

9.3.6.4 Cost of Borrowed Funds ..................................... 205

9.3.6.5 Labor Escalation.................................................. 206

9.3.6.6 Profits  ................................................................. 206     

9.3.6.7 Punitive Damages............................................... 206

9.4 NO-DAMAGE-FOR-DELAY CLAUSES.................................... 206

9.5       VARIOUS DAMAGE PRINCIPLES AND THEORIES IN NEBRASKA       209                             

9.6 CONCLUSION............................................................................ 210                 

 

CHAPTER TEN

LIENS AND BONDS

 

10.1     INTRODUCTION.................................................................. 215

10.2     CONSTRUCTION LIENS – THE NEBRASKA CONSTRUCTION LIEN ACT        216

10.2.1  Scope of NCLA......................................................... 216

10.2.2  Notice Requirements for Filing a Lien....................... 217

10.2.3  Time Limitation for Recording a Lien........................ 217

10.2.4  Required Contents of Lien......................................... 218

10.2.5  Determining the Amount of the Lien.......................... 218

10.2.6  Liens Recorded in Bad Faith..................................... 219

10.2.7  Preventing Attachment of Liens and Bonding Over Filed Liens                    219                 

10.2.8  Amending or Waiving Lien Rights............................. 220

10.2.9  Enforcement of Construction Lien............................ 220

10.2.10  Determining Lien Priority......................................... 221

10.2.11   Determining Lien Priority – Notice of Commencement     223     

10.3     BONDS.................................................................................. 225                             

10.3.1  State and Local Projects – The Little Miller Act......... 225

10.3.2  Federal Projects – The Miller Act.............................. 226

10.3.3  Private Payment Bonds............................................. 228

10.4     CONCLUSION...................................................................... 229                 

 

CHAPTER ELEVEN

EFFECTIVE COLLECTION TECHNIQUES

 

11.1     INTRODUCTION.................................................................. 233                 

11.2     PREJUDGMENT ATTACHMENT....................................... 233

11.3     PREJUDGMENT GARNISHMENT..................................... 235

11.4     POST JUDGMENT GARNISHMENT IN AID

OF EXECUTION................................................................... 236

11.5     WRITS OF EXECUTION...................................................... 237     

11.6     LIENS ARISING BY OPERATION OF LAW....................... 237

11.7          DORMANCY, REVIVAL, AND EXPIRATION OF JUDGMENTS   238                 

11.8     CONCLUSION...................................................................... 237                 

 

CHAPTER TWELVE

ARBITRATION, MEDIATION, LITIGATION, ALTERNATIVE DISPUTE RESOLUTION & SETTLEMENT

 

12.1     INTRODUCTION.................................................................. 241                 

12.2     ARBITRATION...................................................................... 241                 

12.3     MEDIATION.......................................................................... 244                             

12.4     OTHER ALTERNATIVE DISPUTE RESOLUTION

 METHODS........................................................................... 244                 

12.4.1  Mini-Trials........................................................................ 244                 

12.4.2  Summary Jury Trials....................................................... 244     

12.5     LITIGATION.......................................................................... 245                             

12.5.1  Pleadings......................................................................... 245                 

12.5.2  Discovery......................................................................... 247                 

12.5.3  Settlement........................................................................ 248                 

12.5.4  Prejudgment Interest....................................................... 248     

12.5.5  Summary Judgments...................................................... 250     

12.5.6  Trial.................................................................................. 250                             

12.5.7  Appeal.............................................................................. 251                             

12.6     CONCLUSION...................................................................... 252                 

 

CHAPTER THIRTEEN

BUSINESS ENTITY CHOICES

 

13.1     INTRODUCTION ................................................................. 255     

13.2     STATE LAW CLASSIFICATIONS - CHOICE OF ENTITY. 256

13.2.1  Sole Proprietorship.................................................... 256     

13.2.2  General Partnership................................................... 256     

13.2.3  Limited Liability Partnership....................................... 257

13.2.4  Limited Partnership.................................................... 257     

13.2.5  Limited Liability Company......................................... 257     

13.2.6  C Corporation............................................................ 257                 

13.2.7  S Corporation............................................................. 257                 

13.3     TAX CLASSIFICATION OF ENTITIES................................ 258

13.3.1  “Check-the-Box” Regulations.................................... 258

13.3.1.1     Default Rules........................................... 258

13.3.1.2     Single-Member Entities........................... 258

13.3.1.3     Foreign Entities........................................ 259

13.3.1.4     Change in Classification.......................... 259

13.3.2  Implications of the Check-the-Box Regulations........ 259

13.3.2.1     Use of LLCs............................................. 259

13.3.2.2     Single-Member Entities........................... 259

13.3.2.3     Consolidated Returns.............................. 259

13.3.2.4  Simplification of Organizational

Documents................................................. 259

13.4     TRANSFERS OF PROPERTY TO NEW ENTITIES........... 260     

13.4.1  General Partnership and Limited Partnership........... 260

13.4.2  Limited Liability Company......................................... 260

13.4.3  C Corporation / S Corporation................................... 261

13.5     ENTITY FORMATION AND DOCUMENTATION............... 261

13.5.1  General Partnership................................................... 261     

13.5.2  Limited Partnership.................................................... 262     

13.5.3  Limited Liability Company......................................... 262

13.5.4  S Corporation / C Corporation................................... 262

13.6     ENTITY OPERATIONS........................................................ 262     

13.6.1  General Partnership / Limited Liability Partnership... 262

13.6.1.1     Management............................................ 262

13.6.1.2     Limitation on Liability................................ 263

13.6.1.3     Transferability of Interests....................... 263

13.6.1.4     Affiliates................................................... 263

13.6.1.5     Special Allocations................................... 264

13.6.2  Limited Partnership.................................................... 264     

13.6.2.1     Management............................................ 264

13.6.2.2     Limitation on Liability................................ 264

13.6.2.3     Transferability of Interests....................... 265

13.6.3  Limited Liability Company......................................... 265

13.6.3.1     Management............................................ 265

13.6.3.2     Limitation on Liability................................ 266

13.6.3.3     Transferability of Interests....................... 266

13.6.3.4     Affiliates................................................... 266

13.6.3.5     Special Allocations................................... 265

13.6.4  S Corporation............................................................. 267                 

13.6.4.1     Management............................................ 267

13.6.4.2     Limitation on Liability................................ 267

13.6.4.3     Transferability of Interests....................... 268

13.6.4.4     Affiliates................................................... 268

13.6.4.5     Special Allocations................................... 268

13.6.5  C Corporation............................................................ 268                 

13.6.5.1     Management............................................ 268

13.6.5.2     Limitation on Liability................................ 269

13.6.5.3     Transferability of Interests....................... 269

13.6.5.4     Affiliates................................................... 269

13.6.5.5     Special Allocations................................... 269

13.7     DISTRIBUTIONS OF CASH AND PROPERTY.................. 270

13.7.1  General Partnership / Limited Partnership................ 270

13.7.1.1     Cash Distributions.................................... 270

13.7.1.2     Distributions of Property.......................... 270

13.7.1.3     Self-Employment Tax............................. 271

13.7.2  Limited Liability Company......................................... 271

13.7.2.1     Cash Distributions.................................... 271

13.7.2.2     Distributions of Property.......................... 271

13.7.2.3     Self Employment Tax.............................. 271

13.7.3  S Corporation............................................................. 271                 

13.7.3.1     Cash Distributions.................................... 271

13.7.3.2     Distributions of Property.......................... 273

13.7.3.3     Self-Employment Tax............................. 273

13.7.4  C Corporation............................................................ 273                 

13.7.4.1     Cash Distributions.................................... 273

13.7.4.2     Distributions of Property.......................... 273

13.8     LIQUIDATION AND TERMINATION................................... 274

13.8.1  General Partnership / Limited Liability Partnership... 274

13.8.2  Limited Partnership.................................................... 275     

13.8.3  Limited Liability Company......................................... 275

13.8.4  S Corporation............................................................. 275                 

13.8.5  C Corporation............................................................ 275                 

13.9     CURRENT ISSUES FOR CONTRACTORS AND DESIGN PROFESSIONALS - AMERICAN JOBS CREATION ACT OF 2004.................................................... 275                                         

13.9.1  Deduction for Domestic Producers................................. 276     

13.9.2  S Corporations................................................................. 276     

13.10   PERSONAL LIABILITY FOR CORPORATE DEBTS......... 276

13.11   CONCLUSION...................................................................... 277                 

 

CHAPTER FOURTEEN

INSURANCE

 

14.1     INTRODUCTION.................................................................. 281     

14.2     COVERAGES AND EXCLUSIONS..................................... 281

14.2.1  Commercial General Liability Policies............................. 281

14.2.2  Coverages....................................................................... 282                 

14.2.2.1     Bodily Injury or Property Damage

14.2.2.1.1  Bodily Injury....................................... 283

14.2.2.1.2  Property Damage`............................. 283

14.2.2.2     Diminution in Value........................................ 284

14.2.2.3     Loss of Use.................................................... 285

14.2.2.4     Removal of Defective Work ......................... 286

14.2.3  Occurrence     ................................................................. 288

14.2.3.1     Faulty Work as an Occurrence..................... 288

14.2.3.2     Occurrence Must Actually Cause

Damage................................................... 289

14.2.3.3     ISO Additional Insured Endorsement...... 289

14.2.4  Exclusions........................................................................ 291     

14.2.4.1     Damage to Property ..................................... 291

14.2.4.2     Exclusion (j)(5)............................................... 292

14.2.4.3     Exclusion (j)(6)............................................... 292

14.2.4.4     Damage to Your Product............................... 293

14.2.4.5     Damage to Your Work .................................. 294

14.2.4.6     Damage to Property Not Physically

Injured ..................................................... 294

14.2.4.7.... Recall of Products, Work, or Impaired Property 296

14.2.4.8.... Endorsement Excluding Professional Liability     297

14.2.5  Policy Conditions............................................................. 298

14.2.5.1     Cooperation and Timely Notice..................... 298

14.2.5.1.1  Payment ........................................... 298

14.2.5.1.2  Burden of Proof................................. 299

14.2.5.1.3  Attorneys’ Fees.................................. 299

14.2.5.2     Builder’s Risk Policy...................................... 300

14.2.5.3     Professional Liability Policy........................... 301

14.2.5.4     Wrap-Up Policy ............................................ 301 

14.2.6  Additional Insured and Indemnity Obligations................. 302

14.2.6.1     Insured Obligations........................................ 302

14.2.6.2     Indemnity Obligations.................................... 302

14.3          CONCLUSION...................................................................... 303     

 

CHAPTER FIFTEEN

Construction Lending

 

15.1     INTRODUCTION ................................................................. 307     

15.2     LOAN DOCUMENTATION.................................................. 307     

15.2.1  Notice of Duty to Pay Claims.......................................... 308

15.2.2  Preserving Priorities of Subsequent Advances on the Construction Loan    308     

15.2.3  Loan Funding and Disbursements................................... 310

15.2.4 Change Orders................................................................ 311                 

15.2.5  Lien Waivers   ................................................................. 311     

15.2.6  Final Inspection and Closing or Sale............................... 311

15.3     THE LENDER’S RESPONSE TO LIEN FILINGS............... 312

15.3.1  Responding to the Recording of a

Construction Lien....................................................... 312

15.3.2  Enforcing Loan Documents....................................... 313

15.3.3  Avoiding Involvement with Third Party Disputes....... 313

15.3.4  Lender’s Legal Options in Response to a Construction Lien  315                             

15.3.5  Securing the Project.................................................. 316     

15.3.6  Enforcement Options................................................ 316     

15.4     CONCLUSION                       318

 

 

TOP